濟南電纜橋架安裝全流程注意事項解析

  電纜橋架作為電力與通信線路的重要載體,其安裝質量直接影響系統運行與使用壽命。從施工準備到驗收交付,每個環節均需嚴格遵循技術規范,確保橋架系統穩固可靠。

  As an important carrier of power and communication lines, the installation quality of cable trays directly affects the safety and service life of the system operation. From construction preparation to acceptance and delivery, every step must strictly follow technical specifications to ensure the stability and reliability of the bridge system.

  安裝前需對施工環境進行勘查。確認建筑結構承重能力,混凝土強度需達到C20以上方可進行膨脹螺栓固定。對于鋼結構廠房,需檢測橫梁撓度,確保橋架荷載不超過設計值的70%。環境溫濕度同樣關鍵,低溫環境下金屬橋架收縮率可達0.02%/℃,需預留熱脹冷縮補償量;潮濕區域則需選用鍍鋅厚度≥65μm的橋架,防止銹蝕。

  A comprehensive survey of the construction environment is required before installation. The key is to confirm the load-bearing capacity of the building structure, and the concrete strength must reach C20 or above before expansion bolt fixation can be carried out. For steel structure factories, it is necessary to detect the deflection of the crossbeam to ensure that the bridge load does not exceed 70% of the design value. The temperature and humidity of the environment are equally critical. The shrinkage rate of metal cable trays can reach 0.02%/℃ in low-temperature environments, and compensation for thermal expansion and contraction needs to be reserved; In damp areas, cable trays with a galvanized thickness of ≥ 65 μ m should be selected to prevent rusting.

  工具與材料驗收是質量控制的首道關卡。電動扳手扭矩需校準±5%,確保M10螺栓緊固力矩達標。橋架本體檢測需涵蓋外觀、尺寸與鍍層厚度,使用涂層測厚儀隨機抽檢,鍍鋅層厚度不足60μm或噴塑層附著力不達1級標準的產品禁止使用。跨接導線需采用4mm2銅編織帶,截面積不足將影響接地連續性。

  The acceptance of tools and materials is the first hurdle in quality control. The torque of the electric wrench needs to be calibrated to ± 5% to ensure that the tightening torque of the M10 bolt meets the standard. The inspection of the bridge body should cover appearance, size, and coating thickness. A coating thickness gauge should be used for random sampling. Products with a galvanized layer thickness of less than 60 μ m or a spray coating adhesion that does not meet Level 1 standards are prohibited from use. The jumper wire needs to use 4mm 2 copper braided tape, and insufficient cross-sectional area will affect grounding continuity.

  定位劃線階段需建立三維坐標系。水平誤差每米不得超過2mm,全長偏差控制在10mm以內,使用激光投線儀配合墨斗彈線。轉角處需采用45°拼接工藝,避免直角彎頭造成的線路磨損。對于多層橋架,垂直間距需預留200mm以上,便于散熱與維護,底部距地面高度不宜低于2.5米,防止機械損傷。

  The positioning and marking stage requires the establishment of a three-dimensional coordinate system. The horizontal error shall not exceed 2mm per meter, and the overall deviation shall be controlled within 10mm. A laser projector shall be used in conjunction with an ink fountain to mark the line. 45 ° splicing technology should be used at the corner to avoid line wear caused by right angle bends. For multi-layer cable trays, a vertical spacing of at least 200mm should be reserved for heat dissipation and maintenance. The bottom should not be less than 2.5 meters above the ground to prevent mechanical damage.

20221114120958540.jpg

  支吊架安裝是確保橋架穩定性的核心環節。膨脹螺栓埋深需達到80mm以上,使用扭矩扳手分兩次緊固,達到設計值70%,二次復緊間隔24小時。吊架間距需根據橋架規格調整,200mm寬橋架間距不得超過1.5米,超過400mm寬需增設縱向抗震支吊架。對于非直線段,每3米需增設固定支架,防止變形。

  The installation of supports and hangers is the core link to ensure the stability of the bridge. The burial depth of the expansion bolt should be at least 80mm, and it should be tightened twice with a torque wrench. The first tightening should reach 70% of the design value, and the second tightening should be spaced 24 hours apart. The spacing between hangers should be adjusted according to the specifications of the bridge frame. The spacing between 200mm wide bridge frames should not exceed 1.5 meters, and longitudinal seismic support hangers should be added if the width exceeds 400mm. For non-linear sections, fixed brackets should be added every 3 meters to prevent deformation.

  橋架組裝需遵循“先下后上、先內后外”原則。連接板螺栓緊固順序需對稱交叉進行,避免單邊受力導致密封不嚴。蓋板安裝前需清理內部雜物,使用吸塵器配合粘毛滾筒,防止金屬碎屑損傷電纜絕緣層。對于防火橋架,需檢查防火封堵是否嚴密,防火泥填充率需達95%以上,孔洞處需加裝防火包。

  The assembly of cable trays should follow the principle of "from bottom to top, from inside to outside". The tightening sequence of the connecting plate bolts should be symmetrically crossed to avoid insufficient sealing caused by unilateral force. Before installing the cover plate, it is necessary to clean the internal debris and use a vacuum cleaner in conjunction with a glue roller to prevent metal debris from damaging the cable insulation layer. For fireproof cable trays, it is necessary to check whether the fireproof sealing is tight, the fireproof mud filling rate should be above 95%, and fireproof bags should be installed at the holes.

  接地處理是保障系統的關鍵步驟。每段橋架需保證2處以上接地連接,跨接導線與橋架接觸面需去除鍍層,露出金屬本色后涂抹導電膏。總等電位聯結箱接地電阻不得大于1Ω,使用接地電阻測試儀分三次測量取平均值。對于強電與弱電共架場景,需采用分隔板隔離,間距保持300mm以上,防止電磁干擾。

  Grounding treatment is a crucial step in ensuring system safety. Each section of the bridge should ensure at least 2 grounding connections, and the contact surface between the jumper wire and the bridge should have its coating removed. After exposing the natural color of the metal, conductive paste should be applied. The grounding resistance of the total equipotential bonding box shall not exceed 1 Ω, and the grounding resistance tester shall be used to measure the average value in three separate measurements. For the scenario of strong and weak electricity sharing the same frame, a partition board should be used for isolation, with a spacing of at least 300mm to prevent electromagnetic interference.

  特殊環境安裝需采取專項措施。腐蝕性區域橋架需做三防處理,底漆干膜厚度≥50μm,面漆耐鹽霧性能需達720小時以上。高溫場所應選用耐溫150℃以上的硅橡膠密封條,橋架頂部需加裝隔熱板。振動設備附近需安裝彈性支架,固有頻率避開設備振動頻率50%以上,避免共振導致的疲勞損傷。

  Special measures need to be taken for installation in special environments. Corrosive area cable trays need to undergo three protection treatments, with a dry film thickness of ≥ 50 μ m for the primer and a salt spray resistance of at least 720 hours for the topcoat. Silicone rubber sealing strips with a temperature resistance of 150 ℃ or above should be used in high-temperature places, and insulation boards should be installed on the top of the bridge. Elastic supports should be installed near vibration equipment, with natural frequencies avoiding over 50% of the equipment's vibration frequency to prevent fatigue damage caused by resonance.

  驗收階段需進行多維度檢測。外觀檢查采用5倍放大鏡,查看焊縫、涂層缺陷。載荷試驗需加載設計值的150%,持續2小時無變形。接地連續性測試需在潮濕環境下進行,確保接觸電阻≤0.01Ω。提交的竣工資料需包含三維走向圖、材料合格證及第三方檢測報告,實現全生命周期可追溯。

  Multi dimensional testing is required during the acceptance stage. The appearance inspection adopts a 5x magnifying glass, focusing on inspecting weld seams and coating defects. The load test needs to be loaded to 150% of the design value for 2 hours without permanent deformation. The grounding continuity test should be conducted in a humid environment to ensure that the contact resistance is ≤ 0.01 Ω. The submitted completion documents must include a three-dimensional directional diagram, material qualification certificate, and third-party inspection report to achieve full lifecycle traceability.

  本文由濟南電纜橋架友情奉獻.更多有關的知識請點擊  http://m.h3022.cn   真誠的態度.為您提供為的服務.更多有關的知識我們將會陸續向大家奉獻.敬請期待.

  This article is a friendly contribution from Jinan Cable Bridge For more related knowledge, please click http://m.h3022.cn Sincere attitude To provide you with comprehensive services We will gradually contribute more relevant knowledge to everyone Coming soon.山東電纜橋架

 
qq
售前咨詢熱線
15168870138
售后咨詢熱線
13465410318
主站蜘蛛池模板: 开云(中国)Kaiyun·官方网站-登录入口 | 广州企亚 - 数码直喷、白墨印花、源头厂家、透气无手感方案服务商! | 工业设计,人工智能,体验式3D展示的智能技术交流服务平台-纳金网 J.S.Bach 圣巴赫_高端背景音乐系统_官网 | 定坤静电科技静电消除器厂家-除静电设备 | 多功能真空滤油机_润滑油全自动滤油机_高效真空滤油机价格-重庆润华通驰 | 北京网站建设-企业网站建设-建站公司-做网站-北京良言多米网络公司 | 单锥双螺旋混合机_双螺旋锥形混合机-无锡新洋设备科技有限公司 | 超声波成孔成槽质量检测仪-压浆机-桥梁预应力智能张拉设备-上海硕冠检测设备有限公司 | CCC验厂-家用电器|服务器CCC认证咨询-奥测世纪 | 制氮设备_PSA制氮机_激光切割制氮机_氮气机生产厂家-苏州西斯气体设备有限公司 | 户外-组合-幼儿园-不锈钢-儿童-滑滑梯-床-玩具-淘气堡-厂家-价格 | 成都顶呱呱信息技术有限公司-贷款_个人贷款_银行贷款在线申请 - 成都贷款公司 | 砂磨机_立式纳米砂磨机_实验室砂磨机-广州儒佳化工设备厂家 | 高温链条油|高温润滑脂|轴承润滑脂|机器人保养用油|干膜润滑剂-东莞卓越化学 | 氧化锆纤维_1800度高温退火炉_1800度高温烧结炉-南京理工宇龙新材料股份有限公司 | 哈希余氯测定仪,分光光度计,ph在线监测仪,浊度测定仪,试剂-上海京灿精密机械有限公司 | 稳尚教育加盟-打造高考志愿填报平台_新高考志愿填报加盟_学业生涯规划加盟 | 石家庄律师_石家庄刑事辩护律师_石家庄取保候审-河北万垚律师事务所 | 2025福建平潭岛旅游攻略|蓝眼泪,景点,住宿攻略-趣平潭网 | 宽带办理,电信宽带,移动宽带,联通宽带,电信宽带办理,移动宽带办理,联通宽带办理 | LCD3D打印机|教育|桌面|光固化|FDM3D打印机|3D打印设备-广州造维科技有限公司 | 亮点云建站-网站建设制作平台 | ★店家乐|服装销售管理软件|服装店收银系统|内衣店鞋店进销存软件|连锁店管理软件|收银软件手机版|会员管理系统-手机版,云版,App | 石家庄律师_石家庄刑事辩护律师_石家庄取保候审-河北万垚律师事务所 | 食药成分检测_调料配方还原_洗涤剂化学成分分析_饲料_百检信息科技有限公司 | 太空舱_民宿太空舱厂家_移动房屋太空舱价格-豪品建筑 | 有声小说,听书,听小说资源库-听世界网 | 警方提醒:赣州约炮论坛真的安全吗?2025年新手必看的网络交友防坑指南 | 北京晚会活动策划|北京节目录制后期剪辑|北京演播厅出租租赁-北京龙视星光文化传媒有限公司 | 医疗仪器模块 健康一体机 多参数监护仪 智慧医疗仪器方案定制 血氧监护 心电监护 -朗锐慧康 | 哈希PC1R1A,哈希CA9300,哈希SC4500-上海鑫嵩实业有限公司 | 登车桥动力单元-非标液压泵站-非标液压系统-深圳市三好科技有限公司 | 定做大型恒温循环水浴槽-工业用不锈钢恒温水箱-大容量低温恒温水槽-常州精达仪器 | 浴室柜-浴室镜厂家-YINAISI · 意大利设计师品牌 | 咿耐斯 |-浙江台州市丰源卫浴有限公司 | 土壤检测仪器_行星式球磨仪_土壤团粒分析仪厂家_山东莱恩德智能科技有限公司 | 彩超机-黑白B超机-便携兽用B超机-多普勒彩超机价格「大为彩超」厂家 | 珠光砂保温板-一体化保温板-有釉面发泡陶瓷保温板-杭州一体化建筑材料 | 防爆电机生产厂家,YBK3电动机,YBX3系列防爆电机,YBX4节防爆电机--河南省南洋防爆电机有限公司 | 升降机-高空作业车租赁-蜘蛛车-曲臂式伸缩臂剪叉式液压升降平台-脚手架-【普雷斯特公司厂家】 | 陕西华春网络科技股份有限公司| 全自动不干胶贴标机_套标机-上海今昂贴标机生产厂家 |